Road Closure on Jamieson Avenue

Pedestrian and vehicular traffic will be restricted until January 2024.

To prevent combined sewage from polluting and harming local waterways, RiverRenew crews must upgrade the Hooffs Run Interceptor at our construction sites north of Jamieson Avenue and within African American Heritage Park.

RiverRenew crews must fully close Jamieson Avenue to through pedestrian and vehicular traffic while they work to connect these two areas.

What to Expect:

  • Last week of August: Intermittent single lane and sidewalk closures during work hours (7 a.m. - 6 p.m.)

  • First week of September: Single lane and sidewalk closures during work hours (7 a.m. - 6 p.m.)

  • First week of October through January 2024: Full closure of Jamieson Avenue (24/7)

  • Detour signs re-routing vehicular, bicycle, and pedestrian traffic

  • Fencing and barriers across Jamieson Ave

  • Uninterrupted access to businesses along Jamieson Ave

*Schedule is generalized and subject to change.

Learn more and download a project flyer