The City of Alexandria plans to mill and repave:

  • Englehardt Lane from Jamieson Avenue to End from October 3 to October 10 9:00 am to 3:30 pm

  • Jamieson Avenue from Andrew’s Lane to Holland Lane from October 4 to October 11 9:00 am to 3:30 pm

  • John Carlyle Street from Eisenhower Avenue to Duke Street from October 6 to October 13 9:00 am to 3:30 pm

The work will occur in 3 block sections with the intent to complete each section within 4 days, excluding weekends, weather permitting. Scheduling is highly dependent on weather conditions.

Please be aware of the following during this project:

  1. No vehicles may be parked on the affected street sections during the work. Temporary No Parking signs will be posted prior to any construction activity. In the event of delays, temporary signs will be adjusted accordingly.

  2. Traffic in the immediate and surrounding area may need to be re-directed. Please observe traffic detours and other traffic signs.

  3. City T&ES staff will be on the scene for the duration of the project.

  4. Streets will be re-striped as soon as practical following resurfacing.

  5. Posted sign dates are subject to change and will be updated accordingly.